Project

Installation of SCADA Sismored at UDESA

Installation and launch of a Sismored Telemetry and Remote Control Platform at UDESA Distributor.

The project involves the installation of remote control and telemetry equipment in the 50 most important distribution centres at the power company. In addition, a Video Wall consisting of 4 40" screens with a resolution of 3960x2160 pixels has been installed in the Control Centre, on which the entire UDESA distribution network is shown.

UDESA is an electrical distributor in Santiago de Compostela and serves several neighbouring town halls (Ordes, Oroso, Cerceda, etc.). It that has more than 300 Medium to Low Voltage Transformer Centres in its network.

Subir